Hi Erman,
thank you very much for your help.
Actually my adop status is completed for all:
PREPARE COMPLETED
APPLY COMPLETED
FINALIZE COMPLETED
CUTOVER COMPLETED
CLEANUP COMPLETED
The cleanup was released in quick mode.
I have to apply another patch while application must keep running. Should I :
- start another cycle adop from prepare phase and apply the patch
- or apply it in "hotpatch" mode
Regards,
Latifa